How common are data book rejections?
Data book rejections are common enough that most suppliers have money waiting on them. In a 2016 DocBoss survey of 106 suppliers and EPCs, only 1 in 4 suppliers said most of their documents were approved on first submission, and 75% reported documentation-related payment holdbacks. The survey is old and small, so treat it as directional.
The money is real. On EPC projects, retention of about 10% of PO value is typical for valves, pressure vessels and rotating equipment, released against conditions that include final documentation (Project Materials). In the same DocBoss survey, only 30% of suppliers listed documentation as a line item on their proposals, which means the cost of rework is mostly absorbed.
A rejection tells you something failed. It rarely tells you why in a way you can prevent next time. Sorting every finding into one of four classes does.
| Class | What it asks | Common casting and forging examples |
|---|---|---|
| 1. Contract conformance | Does the book match the order? | Wrong PO line; old drawing revision; certificate type 3.1 where 3.2 was ordered; quantity on certificates differs from PO |
| 2. Standard conformance | Are the values inside the limits? | Charpy at the wrong test temperature; hardness over the buyer's maximum; limits for the wrong thickness band applied |
| 3. Traceability | Is it the same identity everywhere? | Heat number on the NDT report differs from the certificate; test bar not tied to a heat treatment lot; serial missing |
| 4. Formal validity and format | Is the package acceptable as a document? | Unsigned certificate; missing even pages from a double-sided scan; wrong index order; no bookmarks; wrong language |
Contract conformance: does the book match the PO?
A contract conformance finding means the book does not match what was ordered: the PO number and line, the part number and revision, the quantity, the material grade, or the EN 10204 certificate type. These are the cheapest findings to prevent and among the most frequent, because the information exists on day one.
Typical contract conformance findings on a casting order:
- Drawing revision. The dimensional report is against revision C; the PO line says revision D.
- Certificate type. The PO asks for EN 10204 3.2; the book has a 3.1 because the inspector was never booked.
- Grade. The PO says ASTM A216 WCC; the certificate says WCB. Or the buyer accepts a comparable EN grade, but only on some lines.
- Quantity. Certificates cover 40 castings; the PO line is for 42, or 2 were scrapped and replaced from a different heat that is missing from the book.
- Special clauses. "Charpy at minus 46 °C on every heat" in the buyer's quality clauses, but not repeated on the PO, is easy to miss.
Prevention: confirm every PO line, revision, quantity, grade and certificate type on one screen at order entry, and copy the buyer's special clauses word for word into the requirements for that order.
How the requirements card handles special clauses
Standard conformance: are the values inside the limits?
A standard conformance finding means a reported value is outside the limit that applies to it. For castings and forgings that limit depends on the grade, the edition of the standard, the governing section thickness and, for impact tests, the test temperature. Most of these findings come from applying the right standard with the wrong condition.
Where castings and forgings catch people out:
- Thickness bands. Many casting and forging standards give different property limits for different section thicknesses. A certificate checked against the thin-section band can pass on paper and fail for a 120 mm flange.
- Test temperature. A Charpy result at minus 20 °C does not satisfy a requirement at minus 40 °C, whatever the energy. For ferritic ductile iron, the EN 1563 LT grades carry their own guaranteed test temperatures.
- Supplementary requirements. ASTM casting specifications let the purchaser add supplementary requirements in the order. If the PO invokes one, its limits apply even though the base specification does not mention them.
- Edition. The buyer's specification may name an edition. A value that passes the current edition may fail the one ordered.
- Buyer limits. Hardness maximums for sour service, or carbon equivalent limits, often come from the buyer, not the material standard.
Prevention: keep limits by grade, edition and thickness band, from your own licensed copies, and check against them in code rather than by eye. Never take a limit from memory, a supplier's datasheet or an AI chat.
Traceability: is it the same heat on every page and on the part?
A traceability finding means the chain of identity breaks: the heat number, heat treatment lot, test bar or serial differs between documents, or between a document and the marking on the part. A buyer cannot accept results that cannot be tied to the castings delivered, however good the values are.
Common traceability breaks for castings:
- Transcription. One digit wrong on one NDT report, usually on the one report that is typed by hand rather than printed from the lab system.
- Mixed heat treatment loads. Castings from three heats share one furnace load. The certificate for heat A references a furnace chart that does not list it.
- Orphan test bars. The test bar result exists, but nothing shows which heat or which heat treatment lot the bar came from.
- Replacement castings. A scrapped casting is replaced from a later heat, and the book still shows only the original heat.
- Certificate against source record. The certificate says 0.21% carbon; the spectrometer printout for that heat says 0.23%. Both are "the same heat", but they disagree.
Prevention: check identities across every document, not just on the certificate, and check each certificate value against its source record at the precision printed.
Heat number traceability for castings
Formal validity and format: is the package itself acceptable?
A formal validity and format finding means the package fails as a document, regardless of the values. Signatures, stamps and issuer identity, legibility, missing or blank pages, the index order, bookmarks and language all fall here. These findings feel trivial, but they send books back as often as technical ones.
Typical formal findings:
- Certificate unsigned, or signed by someone not on the authorized list.
- Inspector's stamp missing on a 3.2.
- Even-numbered pages lost because a double-sided original was scanned single-sided (Energies Media names this as a common mistake).
- A page scanned so faint that values cannot be read.
- Sections out of the buyer's index order, or no bookmarks in the PDF.
- Documents in a language the PO does not accept, without a translation.
- A priced PO left in the book.
Prevention: run package checks before anyone reads values: page count, blank and duplicate pages, locked or unreadable files, then the index against the agreed order.
Can a data book review catch a forged certificate?
No document review can reliably catch a well-made forgery. A review can check that a certificate agrees with its own source records, that identities match and that values sit inside limits. When the documents cannot settle a question, the answer is a physical check on the part, such as PMI or a hardness test.
The stakes are real. The US Navy spent nearly $14 million and about 50,000 engineering hours assessing submarine castings after the director of metallurgy at a steel foundry falsified strength and toughness test results for more than 240 productions of steel (US Department of Justice, 2022). Project Materials puts the general point plainly: a certificate can be fraudulent or attached to the wrong product, and PMI exists to verify the material itself.
What a careful review can still do:
- Check the certificate against the spectrometer printout and test reports behind it.
- Flag signatories not on the authorized list.
- Say clearly when the evidence is not enough, and recommend PMI or hardness checks.
How do you stop the same rejection happening again?
You stop a rejection recurring by fixing the step where the evidence was lost, not the book where it was noticed. Most casting and forging findings trace back to order entry or production, weeks before compilation. Record the class of every finding, then move the check that would have caught it to the earliest possible step.
- Classify each finding from the rejection into one of the four classes.
- For contract findings, add the missing requirement to the customer's standing requirements so the next PO starts with it.
- For standard conformance findings, check that the limit used was for the right grade, edition, thickness band and test temperature.
- For traceability findings, find where the identity changed and add a check at that handoff (melt shop to lab, lab to furnace, furnace to NDT).
- For formal findings, add a package check before compilation.
- Send the index and compliance matrix to the buyer for approval with the next order acknowledgment.
What this means for your data book
- Sort every finding into the four classes, so causes become visible across orders.
- Prevent contract findings at order entry, not at compilation.
- Keep limits by grade, edition, thickness band and test temperature.
- Check identities across every document, and each certificate against its source records.
- Run package checks before anyone reviews values.
How to check a data book, step by stepWhat goes in a manufacturer's data bookData book software for foundries and forgesData book review for buyers and inspectors
Sources
Sources are listed in the order they are cited. Standards are cited by number and clause; consult your own licensed copy for their requirements.
- DocBoss, "What do suppliers think?" (2016 survey of 45 suppliers and 61 EPCs). docboss.com/blog/what-do-suppliers-think
- Project Materials, "Payment milestones in EPC projects". blog.projectmaterials.com/quick-answers/epc/payment-milestones-epc-projects
- Energies Media, "Effective final review strategies for manufacturing record books and turnover packages". energiesmedia.com/effective-final-review-strategies-for-manufacturing-record-books-and-turnover-packages
- US Department of Justice, Western District of Washington, "Former lab director sentenced to prison for falsifying results of steel testing for parts of Navy subs" (14 February 2022). www.justice.gov/usao-wdwa/pr/former-lab-director-sentenced-prison-falsifying-results-steel-testing-parts-navy-subs
- Project Materials, "PMI testing vs MTC". blog.projectmaterials.com/quick-answers/epc/pmi-testing-vs-mtc
- Applus+ Laboratories materials portal, EN-GJS-350-22-LT datasheet (impact test temperature). www.appluslaboratories.com/materials-portal/datasheet/en-gjs-350-22-lt-en-js1015/1644309248
- ASTM International, A703/A703M "Steel Castings, General Requirements, for Pressure-Containing Parts" (scope: supplementary requirements apply when specified in the order). store.astm.org/a0703_a0703m-07.html