A manufacturer's data book is the permanent quality record that travels with a part or piece of equipment after delivery. It proves, document by document, that what was delivered matches what was ordered: the right material, the right heat treatment, the required tests, and an unbroken link between every record and the physical part.

Project Materials describes a data book as a compiled set of documents recording the complete manufacturing, inspection and testing history of supplied equipment, and as a permanent quality record that follows the equipment through its operational life. That last part matters most. A data book is not paperwork for shipment day. It is what an engineer opens ten years later when a valve body cracks, or when an auditor asks which heat a pressure part came from.

What does MRB mean in oil and gas documentation?

In oil and gas, power and pressure equipment documentation, MRB means manufacturing record book: the data book for a supplied item. It does not mean Material Review Board, the quality committee that decides what to do with nonconforming material. Both terms appear in the same quality systems, so write "manufacturing record book (MRB)" on first use.

The International Association of Drilling Contractors published a standard MRB structure for drilling equipment (IADC, 2016). Its four sections are a useful reference for any MRB: finished product documentation, certifying authority documentation, traceability and manufacturing documentation organized by part number, and supplementary documentation. The IADC guidance also asks that every document carry traceability information, such as part number, serial number, heat number or PO number, on each page.

MDB vs MRB vs quality dossier vs turnover package: what is the difference?

MDB, MRB, quality dossier, vendor data book and turnover package mostly name the same thing from different industries and different points in the project. The content overlaps almost entirely. What changes is who asks for it, when it is due and how much of the wider project it covers.

Common names for a data book and where you meet them
TermWhere you meet itUsual scopeTypical point of delivery
Manufacturer's data book (MDB)Valve, pump and pressure equipment buyers; EPC purchase ordersOne item or one PO, from the manufacturerWith or shortly after shipment
Manufacturing record book (MRB)Oil and gas, drilling equipment, subseaOne assembly or part number, with component records below itWith shipment or at release
Vendor data book (VDB)EPC document control, listed on the VDRL or SDRLAll vendor documents for a PO, including drawings and manualsFinal documentation milestone
Quality dossierEuropean buyers, rail, powerQuality records for the orderWith shipment
Turnover package (TOP)Construction and commissioningA system or area handed over to the owner, including many vendors' booksAt mechanical completion or handover

The VDRL (vendor data requirements list) or SDRL (supplier data requirements list) is the buyer's list of documents a supplier must submit, and when. If your PO has one, it defines the book. If not, the buyer's quality clauses and the requirements on the drawing do.

What goes in a data book for a casting order?

A data book for a casting order holds the evidence that each casting is the right metal, correctly heat treated and tested, free of unacceptable defects, dimensionally correct, and traceable to its heat. The exact list comes from the PO and the buyer's requirements, but the sections below cover most pressure-retaining and industrial castings.

Typical contents of a casting data book (order varies by buyer)
SectionTypical documentsCasting-specific notes
Cover and indexCover with PO, part number and revision, quantity; contents list in the buyer's orderIndex order is set by the buyer, not by the foundry
Compliance matrixOne line per requirement with where the evidence isSee the definition below
Material certificatesEN 10204 3.1 or 3.2, or ASTM certification, per heatState whether test bars were cast-on or separately cast
Chemical analysisSpectrometer printouts per heatThe source record behind the certificate values
Mechanical testsTensile, hardness, Charpy reportsCharpy at the required temperature, for example for LT ductile iron
Heat treatmentFurnace charts per load, heat treatment certificateEvery casting and its test bars mapped to a load
NDTRT, UT, MT, PT reports, per piece where requiredSerial or heat on each report
Weld repair recordsRepair maps, weld procedure and welder qualification references, post-repair NDTOnly where the order or specification calls for them, often for major repairs
Pressure testHydrostatic test reportsOften done after machining, sometimes by the machine shop
DimensionalDimensional reports against the drawing revisionDrawing revision must match the PO
OtherPMI, coating, marking photographs, certificates of conformance, concessionsConcessions with the buyer's approval reference

What goes in a data book for a forging order?

A data book for a forging order follows the same logic as a casting book, with different source records. The certificate covers the heat of steel and the forging's own tests; records add the forging reduction or process route, the heat treatment load, ultrasonic examination of the forged section and test locations taken from the forging or a prolongation.

Typical forging book sections:

  1. Cover, index and compliance matrix.
  2. Steelmaker's certificate for the ingot or bar, passed on unchanged.
  3. Forger's inspection certificate for the forging: chemistry, tensile, hardness and impact results.
  4. Heat treatment charts per load.
  5. UT reports, per piece.
  6. MT or PT reports on finished surfaces.
  7. Dimensional reports.
  8. Marking and traceability records linking piece serial to heat and heat treatment load.

Where the forging is bought from a forge and machined elsewhere, the forge's certificate goes in as issued and the machine shop adds its own records. See the machine shop section of the EN 10204 guide.

What is a compliance matrix in a data book?

A compliance matrix is a table near the front of the data book with one row per requirement and a column saying where the evidence is: document, section and page. It turns a stack of PDFs into something a reviewer can check line by line, and it shows gaps before the buyer finds them.

A useful compliance matrix for castings has these columns: requirement (in the buyer's words), source (PO line, specification clause), evidence document, page, result, and remarks. Issued before production, it doubles as a checklist for the shop floor.

Who approves the data book, and when?

The buyer approves the data book, usually through supplier quality, EPC document control or a third-party inspector acting for them. Approval normally comes after the book is submitted at or after shipment, and payment of any retention often waits for it. Agreeing the index before production is the surest way to shorten that wait.

On EPC projects, retention of about 10% of the PO value is typical for valves, pressure vessels and rotating equipment, released against conditions that include final documentation (Project Materials). Energies Media recommends asking for a cover sheet and table of contents for review before the full book is submitted, and having the third-party inspector review documentation progressively during manufacture.

What this means for your data book

  • Find the document that defines the book: VDRL or SDRL, buyer quality clauses, or the drawing notes.
  • Agree the index order and compliance matrix with the buyer before production.
  • Plan the casting-specific evidence early: test bar type, heat treatment loads, repair maps, per-piece NDT.
  • Keep every certificate as issued, and every page carrying a heat, serial or PO reference.

Sources

Sources are listed in the order they are cited. Standards are cited by number and clause; consult your own licensed copy for their requirements.

  1. Project Materials, "What is a data book?". blog.projectmaterials.com/quick-answers/epc/what-is-data-book
  2. International Association of Drilling Contractors, "IADC Manufacturing Record Book Guidance" (GU-IADC-SC-004, 2016). iadc.org/wp-content/uploads/2016/10/IADC-Standard-Manufacturing-Record-Book_V1.0-2016-10-18-FINAL-V2.pdf
  3. Energies Media, "Effective final review strategies for manufacturing record books and turnover packages". energiesmedia.com/effective-final-review-strategies-for-manufacturing-record-books-and-turnover-packages
  4. Project Materials, "Payment milestones in EPC projects" (retention for valves, pressure vessels, rotating equipment). blog.projectmaterials.com/quick-answers/epc/payment-milestones-epc-projects
  5. NOV, "Manufacturing Record Book General Requirements" (buyer requirement example). www.nov.com/-/media/nov/files/about/our-company-structure/rig/rig-technologies-supplier-resources/manufacturing-record-book-general-requirements-101444171.pdf