Why plan data book evidence before production?

Data book evidence has to be planned before production because most of it can only be created once. A test the inspector did not witness cannot be witnessed later, and a test bar that was scrapped cannot be retested. Planning at the PO turns each requirement into a record someone is responsible for creating.

The cost of getting it wrong lands at the end of the order. On EPC projects, retention of about 10% of the PO value is typical for valves, pressure vessels and rotating equipment, and final documentation is one of the conditions for releasing it (Project Materials). In a 2016 DocBoss survey of 106 suppliers and EPCs, only 1 in 4 suppliers said most of their documents were approved on first submission. That survey is small and old, so treat it as directional.

What goes on a before-production checklist?

A before-production checklist lists every piece of evidence the order will need, what triggers it, when someone must act, and who keeps the record. The triggers come from the PO and the customer's standing requirements: the certificate type, extra mechanical tests, heat treatment, per-heat and per-piece tests, and the documents section.

Evidence to plan before the first pour on a casting order
EvidenceTriggered byAct beforeLost if
Third-party inspector booking3.2 certificate, or witness and hold points in the ITPTests are scheduledTests run without the inspector present
Spectrometer printout per heatAny certificate with chemistryThe heat is pouredThe printout is not saved with its heat number
Test bars per heat, markedMechanical properties on the certificatePouringBars are poured unmarked or mixed between heats
Spare test bars for retestAny mechanical test that might need a retestThe book is approvedSpares are scrapped with the runners and risers
Charpy specimens at the stated temperatureImpact requirement on the PO or the customer's cardMachining of specimensThe test temperature or bar identity is not recorded
Furnace chart and load listHeat treatment requirement, or a chart called for on the POThe load goes inThe chart is overwritten or the load list omits heats and serials
Per-piece NDT reports (RT, UT, MT, PT)Per-piece tests with a named acceptance standardFinal inspectionReports carry no serial, or the procedure is not referenced
Repair weld records and mapsAny repair on a pressure-containing castingThe repair is madeThe repair location and serial are not recorded
Marking transfer recordMarking removed during fettling or machiningThe marking is removedIdentity on the part cannot be shown
Hydro test, PMI, dimensional reportsTests named on the PO or cardFinal inspectionThe report is not tied to the serial
Data book index and compliance matrixThe customer's document requirementsProduction startsThe book is assembled in an order the buyer did not agree

Not every order needs every row. The point is that every row the order does need has an owner and a date before the first pour.

How do hold and witness points change the plan?

Hold and witness points change the plan because they depend on someone outside the foundry. At a hold point, work cannot continue until the inspecting party formally releases it. At a witness point, the inspector may observe, but work is allowed to continue (Aconex). Either way, the inspector needs notice, so the booking belongs on the checklist.

For an EN 10204 3.2 certificate, validation needs both the manufacturer's authorized inspection representative and the purchaser's authorized representative or an inspector designated by official regulations, and the independent party typically observes the testing (LRQA). That makes the inspector's date a production constraint, not an afterthought.

What to record for each inspection point:

  1. Which test or step it covers, by PO line and heat.
  2. Whether it is a hold point or a witness point.
  3. Who the inspector is and how much notice they need.
  4. The planned date and the confirmed date.
  5. Where the signed inspection record will be filed.

Which test bars and specimens should you keep?

Keep marked test bars for every heat, and the spares for retest, until the data book is approved. A bar represents a casting only if it comes from the same heat and went through the same heat treatment load, so the bar's identity matters as much as the bar itself.

Two points from published guidance:

  • ASTM A703, the general requirements specification for steel castings for pressure-containing parts, calls for test coupons cast from the same heat as the castings they represent (ASTM abstract).
  • The Steel Founders' Society of America notes that test bars should be heat treated in production furnaces with the castings they represent. A bar treated in a later load represents that later load.

When should the buyer approve the data book index?

The buyer should approve the data book index and compliance matrix before production starts. The index fixes the section order the book will follow, and the compliance matrix shows which evidence answers each requirement. Agreeing both early means the book is assembled once, in an order the buyer has already accepted.

Freeze each issue of the index once it is sent, and record the buyer's reply against that issue. If the buyer changes a requirement later, issue a new revision rather than editing the old one, so it is always clear which version the book was held to.

How do you build the checklist from the PO?

Build the checklist by reading the PO and the customer's standing requirements line by line and writing one row for each piece of evidence they call for. Then give every row an owner and a date, and review the list with production before the first pour.

  1. Confirm the PO lines, quantities, part numbers, material and certificate type (3.1 or 3.2).
  2. Pull in the customer's standing requirements: extra mechanical limits, heat treatment, tests per heat or per piece, documents and index order.
  3. Copy any special clause word for word and mark it "confirm by hand".
  4. Write one row per evidence item, per heat or per piece as the requirement says.
  5. Add hold and witness points from the ITP, with the inspector and notice period.
  6. Give each row an owner and an "act before" step.
  7. Issue the index and compliance matrix to the buyer for approval.
  8. Review the list with the melt shop, lab, heat treatment and NDT before the first pour.

What this means for your data book

  • Write the evidence list on the day the PO is confirmed, not when the castings are ready.
  • Book inspectors for 3.2 certificates and hold points before the tests are scheduled.
  • Mark test bars by heat and load, and keep spares until the book is approved.
  • Save furnace charts with a load list naming heats and serials.
  • Get the index and compliance matrix approved before production.

Common questions about before-production checklists

What is a before-production evidence checklist?

A before-production evidence checklist is a list, made at the PO, of every record a casting order's data book will need, with what triggers each record, when someone must act, and who keeps it. It is built from the PO and the customer's standing requirements and reviewed with production before the first pour.

Is a before-production checklist the same as an ITP?

No. An inspection and test plan (ITP) is agreed with the buyer and sets the inspections, tests, acceptance criteria and hold and witness points. A before-production checklist is the supplier's internal list of the evidence those requirements will produce, with owners and dates. The checklist follows the ITP; it does not replace it.

When should a third-party inspector be booked for a 3.2 certificate?

Book the inspector when the PO is confirmed and the test schedule is known, before the tests are planned. A 3.2 certificate needs validation by an independent party, who typically observes the testing, so a test run without them cannot be validated later.

How long should test bars be kept after testing?

Keep marked spare bars at least until the data book is approved, so a retest is possible if a result is queried. Some buyers and specifications set longer retention; check the PO and your quality procedures.

A checklist makes sure evidence is planned and created. It does not decide whether a result meets the requirement: that comes from your licensed standards, the PO and the people who review and sign.

Sources

Sources are listed in the order they are cited. Standards are cited by number and clause; consult your own licensed copy for their requirements.

  1. Project Materials, EPC payment milestones and retention. blog.projectmaterials.com/quick-answers/epc/payment-milestones-epc-projects
  2. DocBoss, "What do suppliers think?" (2016 survey of 45 suppliers and 61 EPCs). docboss.com/blog/what-do-suppliers-think
  3. Aconex help, "Hold Point / Witness Point". help.aconex.com/implementation/hold-point--witness-point
  4. LRQA, "EN 10204 Type 3.2 Certification: Overview Guide" (2023). assets.lrqa.com/m/65d9b900bbe96532/original/EN-10204-Type-3-2-Overview-Guide-GB-2023.pdf
  5. ASTM International, A703/A703M "Steel Castings, General Requirements, for Pressure-Containing Parts" (abstract). store.astm.org/a0703_a0703m-07.html
  6. Steel Founders' Society of America, "Test Coupons and Casting Properties". www.sfsa.org/publications/testcoupons/tc.pdf