Why check in passes instead of page by page?
Checking in passes means looking for one kind of problem across the whole book at a time, instead of reading every page once and trying to catch everything. Each pass needs a different kind of attention. A reader looking at Charpy values does not notice a missing page, and a reader counting pages does not notice a wrong heat number.
The order of the passes matters. There is no point checking a tensile value against its limit if the certificate turns out to belong to a different heat. Requirements come first because they decide what the book must contain. Package and identity checks come next because they are quick and they invalidate later checks. Values come fourth. Sign-off comes last.
The passes map directly onto the four classes of findings: pass 1 catches contract conformance, pass 2 formal validity and format, pass 3 traceability, and pass 4 standard conformance.
Pass 1: what does the order actually require?
Pass 1 builds the list of what the book must prove, before you open the book. Read the PO line by line, then the buyer's quality clauses and specifications, then the drawing notes, and write down every requirement: grade, certificate type, extra tests and limits, documents, index order and special clauses.
- List each PO line: part number, drawing revision, quantity, material grade.
- Record the EN 10204 certificate type for each line, taking the strictest of PO, buyer specification and design code.
- List extra mechanical requirements beyond the base standard: Charpy (with test temperature), hardness range, others.
- List required heat treatment and whether a furnace chart is required per load.
- List tests per heat and per piece: RT, UT, MT, PT, hydrostatic test, PMI, with extent.
- Note the required documents and their index order from the VDRL, SDRL or buyer instructions.
- Copy special clauses word for word. Do not paraphrase them.
- Leave prices out. The priced PO does not belong in the book or in your checking notes.
Pass 2: is the package complete and readable?
Pass 2 checks the book as a set of documents, before any value is read. Count pages, find blank and duplicate pages, open every file to confirm it is not locked or unreadable, check the index against the agreed order, and confirm that every document required in pass 1 is present.
What to check:
- Pages. All pages of each multi-page document ("page 3 of 6") present. Even pages missing usually means a double-sided original scanned single-sided (Energies Media).
- Blanks and duplicates. Blank scanned pages and the same report included twice.
- Files. Password-locked, corrupted or image-only files nobody can search.
- Legibility. Values readable at normal zoom, stamps and signatures visible.
- Index. Sections in the buyer's order, with bookmarks if the buyer asked for an electronic book.
- Presence. Every document from pass 1 is there, at the extent required (per heat, per piece).
- Exclusions. No priced PO, no internal documents that should not leave the company.
Pass 3: is it the same heat, lot and serial everywhere?
Pass 3 checks that the identities connecting each document to the castings are the same everywhere: heat number, heat treatment load, test bar identity, serial number, part number and PO line. Build a small table of every identity on every document, then look for disagreements. One wrong digit invalidates the evidence on that page.
- For each heat, list every document that should carry its number: certificate, spectrometer printout, test reports, furnace chart, NDT reports.
- Check each one carries the same heat number.
- For each heat treatment load, check the furnace chart lists the heats and serials in it.
- Check each test bar result names its heat and, where properties are certified per load, its load.
- For each serial, check per-piece reports (NDT, hydro, dimensional) carry it.
- Check certificate quantities per heat add up to the PO quantity per line, including any replacement castings.
- Check each certificate value against its source record (spectrometer printout, test report) at the precision printed.
Heat number traceability for castings
Pass 4: are the values inside the right limits?
Pass 4 compares each reported value with the limit that applies to it: for the right grade, the right edition, the right thickness band and, for impact tests, the right test temperature. Take limits from your licensed copy of the standard and from the buyer's requirements, never from memory, a datasheet or a previous book.
What catches people out on castings and forgings:
- Thickness band. Use the governing section thickness of the part to pick the limit row.
- Test temperature. Check the temperature reported for Charpy before checking the energy. For ductile iron LT grades under EN 1563, the guaranteed test temperature is part of the grade.
- Supplementary requirements. If the PO invokes a supplementary requirement of the ASTM casting specification, its limits apply.
- Buyer limits. Hardness maximums and similar buyer limits sit on top of the material standard.
- Comparable grades. Accept an equivalent grade only where the buyer has said so for that line.
- Precision. Compare at the precision printed on the source record. Rounding a value to make it pass is a finding.
Pass 5: who signs, and what goes in the record?
Pass 5 checks the signatures on the documents and then records your own decision. Each 3.1 must be validated by the manufacturer's authorized inspection representative; each 3.2 also needs the second party's validation and stamp. Then write down what you checked, against which requirements and limits, what you found, and sign.
- Check each certificate's signatory against the manufacturer's authorized list.
- For 3.2 certificates, check the inspector's countersignature and stamp.
- Check concessions carry the buyer's approval reference.
- List every finding with its class, document, page and decision.
- Record which version of the requirements you checked against.
- Sign and date the review. If a question cannot be settled from the documents, say so and recommend a physical check such as PMI or hardness.
EN 10204 3.1 vs 3.2, explained for castings and forgings
How should a buyer review a supplier's MRB?
A buyer reviews a supplier's manufacturing record book (MRB) with the same five passes, choosing a review depth that fits the supplier and the scope. Energies Media describes three levels: record review (accept and file), summary review (about an hour) and comprehensive review (4 to 8 hours, line by line against the contract).
| Review level | Use when | Passes to run |
|---|---|---|
| Record review | Rarely recommended; low-risk, non-critical items | Pass 2 only |
| Summary review | Known supplier, standard scope | Passes 1, 2 and 3 in full; pass 4 on critical values |
| Comprehensive review | New or foreign supplier, non-standard scope, critical service | All five passes in full |
Two habits from the same source shorten every buyer review: ask for the cover sheet and table of contents for approval before the full book arrives, and have the third-party inspector review documentation progressively during manufacture rather than only at the end.
The printable checklist
The checklist below condenses the five passes into one table of twenty checks you can print and tick at your desk. Each row names the check, where to look in the book, and the failure most often found there on casting and forging orders.
| # | Check | Where to look | Typical failure |
|---|---|---|---|
| 1 | PO lines, part numbers, revisions, quantities listed | PO, drawing | Old drawing revision |
| 2 | Certificate type per line (strictest of PO, spec, code) | PO, buyer specification | 3.1 supplied, 3.2 ordered |
| 3 | Extra limits recorded (Charpy temperature, hardness) | Buyer quality clauses | Requirement not on PO |
| 4 | Tests per heat and per piece listed | PO, specification | Per-piece NDT done per heat |
| 5 | Special clauses copied word for word | Buyer clauses | Clause paraphrased and lost |
| 6 | All pages present, none blank or duplicated | Every multi-page document | Even pages missing |
| 7 | Files readable, not locked | Every file | Image-only scan, faint copy |
| 8 | Index in buyer's order, bookmarks present | Contents | Foundry's order, not buyer's |
| 9 | Priced PO excluded | Whole book | Priced PO left in |
| 10 | Same heat number on every document for that heat | Certificate, printout, tests, NDT | One digit wrong on NDT report |
| 11 | Every casting mapped to a furnace load | Furnace charts, load lists | Load list missing heats |
| 12 | Test bars tied to heat and load; bar type stated | Test reports, certificate | Bar not tied to load |
| 13 | Quantities per heat add to PO quantity | Certificates | Replacement casting missing |
| 14 | Certificate values match source records | Spectrometer printouts, test reports | Rounded or retyped value |
| 15 | Values within limits for grade, edition, thickness band | Licensed standard, requirements | Wrong thickness band |
| 16 | Charpy at the required test temperature | Impact test report | Warmer temperature tested |
| 17 | Weld repair maps and post-repair NDT where required | Repair records | Map missing for major repair |
| 18 | Machine shop records added, foundry certificate unchanged | Machining, hydro, dimensional reports | Certificate retyped by shop |
| 19 | Signatories authorized; 3.2 countersigned and stamped | Certificates | Unsigned or wrong signatory |
| 20 | Findings recorded, review signed and dated | Review record | No record of what was checked |
This table prints on one landscape page.
What this means for your data book
- Run the passes in order: requirements, package, identities, values, sign-off.
- Write the requirements down before opening the book.
- Never check a value before its identity is confirmed.
- Keep a record of what was checked and against which version of the requirements.
- When the paper cannot answer a question, say so and recommend PMI or hardness checks.
Sources
Sources are listed in the order they are cited. Standards are cited by number and clause; consult your own licensed copy for their requirements.
- Energies Media, "Effective final review strategies for manufacturing record books and turnover packages" (review levels, times, pro tips). energiesmedia.com/effective-final-review-strategies-for-manufacturing-record-books-and-turnover-packages
- International Association of Drilling Contractors, "IADC Manufacturing Record Book Guidance" (structure, traceability on every page, format). iadc.org/wp-content/uploads/2016/10/IADC-Standard-Manufacturing-Record-Book_V1.0-2016-10-18-FINAL-V2.pdf
- LRQA, "EN 10204 Type 3.2 Certification: Overview Guide" (validation roles). assets.lrqa.com/m/65d9b900bbe96532/original/EN-10204-Type-3-2-Overview-Guide-GB-2023.pdf
- Steel Founders' Society of America, "Test Coupons and Casting Properties". www.sfsa.org/publications/testcoupons/tc.pdf
- Project Materials, "PMI testing vs MTC". blog.projectmaterials.com/quick-answers/epc/pmi-testing-vs-mtc
- TechnipFMC, supplier documentation requirements (buyer requirement example). www.technipfmc.com/media/pm4aszg2/gsop-10-0008.pdf